Interstate 64 Widening

The Interstate 64 Widening Project in York and James City counties and Newport News will increase vehicle capacity, resulting in immediate congestion relief along one of the most heavily traveled and congested highway corridors on the Virginia Peninsula. 

Divided into three segments, improvements include widening this section of I-64 from a four-lane section to six-lanes for approximately 21 miles, starting west of Jefferson Avenue (Exit 255) in Newport News to just west of Newman Road (Exit 234) in York County.

VDOT determined that the use of design-build contracting for this project will expedite delivery and ensure timely authorization of federal funding. 

The design-builder will be able to perform final design, right of way acquisition and utility relocation and some construction activities concurrently.

This project contributes to the Preferred Alternative and contributes to the Purpose and Need elements outlined in the Final Environmental Impact Statement (FEIS).

Stay up to date on the latest project information and updates using the following methods.

In Your Inbox:

Sign up to receive I-64 Widening project information by email to receive the latest news, information, traffic advisories and progress updates.

Attend an Upcoming Meeting:

View upcoming meetings about the I-64 Widening Project .

Project Updates:

Read about the latest project news on the News & Information page.

Frequently Asked Questions:

Find answers to the latest frequently asked questions on I-64 Widening Project.

Frequently Asked Questions

How will traffic be affected during construction? Will construction take place at night?

To minimize inconvenience to motorists, no daytime lane closures are planned at this time. 

Lane closures and construction information will be announced weekly throughout the duration of the project. 

Two lanes in each direction will be maintained throughout construction during the day, with temporary lane closures at night as needed.  

The design-builder will develop detailed plans for maintenance of traffic, which may include shifting traffic towards the existing outside shoulder during construction.  

Emergency pull off areas for disabled vehicles will be provided as required.

Will there be trees left in the median? What type of landscaping will be used?

The trees in the median space will be addressed on a case-by-case basis to accommodate stormwater management and cut and fill slopes. The raised median with concrete barriers will utilize context-sensitive design with low maintenance shrubs or bushes.

Will the interchanges be upgraded? 

Modifications to the interchanges are not included as part of this project. However, interchange operations will benefit from the additional capacity of the new lanes on I-64 and the lengthening of the acceleration and deceleration ramps.

How will traffic be impacted on the side roads within the project corridor?

Long-term lane closures will be required on Penniman Road (Route 641), Jefferson Avenue (Route. 143) and Yorktown Road (Route 238). 

These closures are required for bridge pier construction to accommodate the proposed widened roadway section for I-64.

Will the interchange ramps be affected during construction?

Yes, there will be some impacts to the interchange ramps during construction to reconstruct the existing pavement.  

This may include some night-time ramp closures.  These will be publicized in advance.

When will construction begin and how long will the project take to complete?

  • Segment I: Construction began in September 2015, and is expected to be complete by December 2017.
  • Segment II: Construction is scheduled to begin in 2016, and is expected to be complete by July 2019.
  • Segment III: Construction is scheduled to begin in 2018, and is expected to be complete by 2021.

Will the project include fixing the existing travel lanes? 

Yes, the existing pavement will be replaced.

Will construction of Segment II overlap with that of Segment I?

Yes, major construction activities within both projects will overlap by approximately one year.

Project Milestones

Gov. McAuliffe Kicks Off Construction for Widening I-64

Gov. Terry McAuliffe announced today construction has started on the first of three segments to widen Interstate 64. The first segment is a $122 million project that will add a lane and shoulder in each direction for 5.6 miles between Jefferson Avenue and Yorktown Road.

Read article

This important project is a critical step forward in our efforts to build the transportation system businesses and families need to thrive in a new Virginia economy. Terry McAuliffe,